MAHARERA
CA. Mahadev Birla, CA Nipun Singhvi
Sachin Prakash Dhavle v. The Collector of Pune & Ors.
Maharashtra Real Estate Appellate Tribunal, Mumbai | M.A. No. 693/2026 in Appeal AT05/00605/2026 | Connected M.A. Nos. 694, 874 and 1298 of 2026 | Order dated 29 September 2026
This decision deals with an appeal filed by a promoter 674 days beyond the statutory limitation period and the consequent release to a successful allottee of the amount deposited under the proviso to Section 43(5) of the RERA Act. The Tribunal rejected unsubstantiated reasons for delay and examined the promoter’s conduct during the original, non-compliance and recovery proceedings.
Issues:
Whether non-receipt of notices, illness and death in the family, partner absence and oversight amounted to sufficient cause for a delay of 674 days; whether the conduct of the promoter in earlier proceedings and execution was relevant; and whether the allottee could withdraw the Section 43(5) deposit after rejection of condonation and disposal of the appeal.
Fact of the Case
The appellant, Sachin Prakash Dhavle, authorised partner of M/s P. R. Builders & Developers, challenged the order dated 8th April 2024 passed by the Adjudicating Officer, MahaRERA, Pune, in non-compliance proceedings in Complaint No. CC005000000054043 brought by allottee Atul Dilip Bhagwat. The original Authority order had been passed on 4th December 2023.
The allottee stated that the complaint was filed on 3rd March 2020 and the promoter, despite service of notice, remained absent; the original proceedings were therefore conducted ex parte. The promoter also did not participate in the later non-compliance proceedings. The Adjudicating Officer issued the impugned order on 8 April 2024.
The promoter filed its appeal on 14th April 2026, 674 days beyond the limitation period, and sought condonation through M.A. No. 693/2026. It alleged non-receipt of summons and notices, illness and death of the applicant’s grandmother, mental distress, an outstation principal partner, and oversight or lack of knowledge of the order until 1st April 2026. It contended that these circumstances impeded timely instructions and preparation of the appeal.
The allottee opposed the request as vague and unsupported. No death certificate, medical certificate, hospital records or travel documents had been furnished. Meanwhile, enforcement had advanced: an attachment order was passed through the Tahsildar, Mulshi, on 29th September 2025 and an order for sale of the attached property on 1st April 2026. The appeal followed on 14th April 2026, after the sale order. The allottee described this as a dilatory attempt to frustrate recovery of the amount awarded.
The promoter contended that the delay was neither intentional nor deliberate and had occurred because of circumstances beyond the applicant’s control. It was submitted that the applicant had not received the summons or notices relating to the original complaint proceedings. According to the applicant, the absence of proper knowledge of those proceedings prevented timely instructions from being given to the advocate for preparation and filing of the appeal.
The promoter further relied upon the illness and subsequent death of the applicant’s grandmother. It was contended that the applicant was not in a stable mental condition following the bereavement and was therefore unable to attend to the legal proceedings. Another explanation advanced was that one of the principal partners of the partnership firm was stationed outside the relevant location, making it difficult to complete the necessary formalities and instructions for filing the appeal within the prescribed period.
The applicant also pleaded oversight and lack of knowledge regarding the impugned order. In particular, it was submitted that, during the period from 2020 until 1 April 2026, the applicant was unaware of the relevant proceedings and the order sought to be challenged. On these grounds, the promoter requested the Tribunal to exercise its discretionary jurisdiction and condone the delay of 674 days in the interest of justice.
The allottee strongly opposed the application for condonation of delay, contending that the promoter had failed to establish any genuine or sufficient cause for approaching the Tribunal after an inordinate delay. It was submitted that the original complaint had been filed on 3rd March 2020 and that the Authority had passed its order on 4th December 2023. Despite service of notices, the promoter remained absent, and the proceedings were conducted ex parte.
The allottee further pointed out that the promoter had also failed to participate in the subsequent non-compliance proceedings before the Adjudicating Officer, which culminated in the order dated 8th April 2024. Since the promoter failed to comply with the directions, execution proceedings were initiated. A recovery warrant was issued, followed by attachment proceedings conducted through the Tahsildar, Mulshi.
The allottee specifically submitted that an attachment order had been issued on 29th September 2025 and that an order for sale of the attached property was passed on 1st April 2026. Significantly, the promoter instituted the appeal only on 14th April 2026, after the execution proceedings had progressed to the stage of sale of the attached property. According to the allottee, the timing of the appeal demonstrated that the promoter had approached the Tribunal not for bona fide adjudication of the dispute but to obstruct or delay enforcement of the order already passed in favour of the allottee.
The allottee therefore submitted that the explanation was vague, unsubstantiated and insufficient to justify condonation of the delay. The allottee relied upon judicial precedents concerning limitation, sufficient cause and the requirement of bona fide conduct, and requested rejection of the application.
The Tribunal, after examining the pleadings and submissions, observed that the impugned order had been passed on 8th April 2024, whereas the appeal was filed only on 14th April 2026, resulting in a delay of 674 days beyond the prescribed period of limitation.
The Tribunal found that the explanations given by the appellant are insufficient. It specifically observed that the applicant had failed to produce any documentary evidence substantiating the circumstances relied upon for condonation of delay. The Tribunal relied upon the judgment of the Hon’ble Supreme Court in Anshul Aggarwal v. New Okhla Industrial Development Authority, (2011) 14 SCC 579, wherein the Supreme Court emphasised that the special limitation periods prescribed under consumer protection legislation must be respected and that applications seeking condonation of delay require a satisfactory explanation.
Applying the aforesaid principles, the Tribunal held that mere assertions of personal difficulties, without supporting material, could not constitute sufficient cause for condoning such an inordinate delay.
The Tribunal further examined the principles governing the exercise of discretionary powers to condone delay. It referred to the judgment of the Hon’ble Supreme Court in State of Madhya Pradesh v. Ramkumar Choudhary, 2024 SCC Online SC 3617, wherein the Supreme Court reiterated that sufficient cause means an adequate and reasonable explanation for the circumstances that prevented a litigant from approaching the Court within limitation.
The Tribunal noted that although the expression sufficient cause should receive a liberal interpretation in appropriate cases, such interpretation cannot extend to circumstances involving negligence, inaction or absence of bona fides.
The Tribunal also referred to the Supreme Court’s observations in Basawaraj v. Special Land Acquisition Officer, (2013) 14 SCC 81, as reproduced in Ramkumar Choudhary, to emphasise that where a party has remained negligent or inactive, the Court cannot condone an inordinate delay merely by imposing costs or other conditions.
The Tribunal accordingly concluded that a justice-oriented approach cannot be used to defeat the substantive provisions of the law of limitation.
The Tribunal relied upon the judgment of the Hon’ble Madras High Court in S.R. Vedappon and Anr. v. S.P. Ramalingam and Anr., C.M.P. No. 7730 of 2017 in A.S.S.R. No. 34779 of 2017, decided on 11th February 2020. The said judgment emphasised that a litigant seeking condonation of delay must furnish candid and convincing reasons. The power to condone delay is required to be exercised judiciously and not in an arbitrary, vague or fanciful manner.
The Tribunal observed that filing an appeal within limitation is the rule, whereas condonation of delay is an exception. Consequently, the applicant must demonstrate genuine reasons for not approaching the appellate forum within the prescribed period.
In the present case, the promoter had failed to explain the delay satisfactorily. Therefore, the Tribunal found no justification for exercising its discretionary jurisdiction in favour of the promoter.
WITHDRAWAL OF THE PRE-DEPOSIT AFTER DISMISSAL OF THE PROMOTER’S APPEAL.
The Tribunal separately examined Miscellaneous Application No. 874 of 2026 filed by the successful allottee seeking withdrawal of the amount deposited by the promoter in compliance with the proviso to Section 43(5) of the RERA Act. The Tribunal relied upon the judgment of the Hon’ble Supreme Court in M/s. Newtech Promoters and Developers Pvt. Ltd. v. State of U.P. & Ors., Civil Appeal Nos. 6745–6749 of 2021, decided on 11 November 2021. Referring particularly to paragraphs 127, 128 and 136 of the said judgment, the Tribunal observed that the statutory pre-deposit requirement serves an important protective purpose.
The Supreme Court had explained that where a promoter challenges an order directing refund of an amount to an allottee, the pre-deposit requirement ensures that the amount determined by the Authority remains secured during appellate proceedings. The requirement also discourages frivolous or unmeritorious appeals intended merely to postpone compliance with orders passed in favour of allottees. The Tribunal reiterated that the proviso to Section 43(5) is mandatory and that compliance with the statutory pre-deposit requirement is a condition precedent for entertaining an appeal filed by a promoter.
The Tribunal observed that the appeal preferred by the promoter could not survive once the application seeking condonation of delay was rejected. Consequently, there remained no surviving appeal requiring retention of the statutory deposit before the Tribunal. The Tribunal held that the amount deposited by the promoter, which was intended to safeguard the successful allottee’s interest, could be released to the allottee.
Accordingly, the Tribunal allowed Miscellaneous Application No. 874 of 2026 and directed its Registry to release the amount deposited by the promoter under the proviso to Section 43(5) to Respondent No. 4, the successful allottee. The Tribunal thus recognised that the statutory deposit should not remain unnecessarily withheld after the promoter’s challenge had failed on the ground of limitation.
Conclusion
The judgment reinforces the principle that condonation of delay is not a matter of right, and a litigant seeking such relief must demonstrate sufficient cause supported by a credible explanation and relevant evidence.
The Tribunal clarified that a liberal interpretation of limitation provisions cannot be extended to protect a litigant whose conduct demonstrates negligence, inaction or dilatory tactics. The applicant’s conduct during the original proceedings, non-compliance proceedings and subsequent execution proceedings may be taken into consideration while determining whether the explanation for delay is bona fide.
The judgment also highlights the protective purpose of the mandatory pre-deposit requirement under Section 43(5) of the RERA Act. Where the promoter’s appeal is dismissed on the ground of limitation, the Tribunal may direct release of the amount deposited by the promoter to the successful allottee, thereby facilitating enforcement of the order passed by the Regulatory Authority.
The decision is particularly relevant in RERA execution proceedings where promoters file belated appeals after attachment or sale proceedings have commenced, and in cases where successful allottees seek withdrawal of the statutory pre-deposit following dismissal of the promoter’s appeal.